1. The three types of estimates on the Three point estimate are Optimistic, Pessimistic and __________
a. Likely
b. Unlikely
c. Equally
d. Unequally
2. What is the most common type of dependency between activities?
a. finish-to-start
b. start-to-finish
c. finish-to-finish
d. start-to-start
3. The amount of time an activity can be delayed and yet not delay the project is termed
a. Total slack.
b. Free slack.
c. Critical float.
d. Float pad.
e. Slip pad.
4. Which of the aspects of a project could be changed after resource leveling?
a. The cost of a particular resource
b. The scope of project
c.The number of tasks in the Work Breakdown Structure
d. The amount of resources of the whole project
e.The start and the end dates of tasks
5. The highest element in the hierarchical breakdown of the WBS is ____________
a. The entire project
b.Major deliverables.
c.A cost account.
d.Sub-deliverables.
e. A work package.
6. Which of the following diagrams is the preferred technique for showing activity sequencing?
a. Network Diagram
b. Tree diagram
c. Venn Diagram
d. Three-dimensional diagram
7. The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following dependencies between “pouring concrete” and “construction” activities
a. Finish to Start
b. Start to Start
c. Start to Finish
d.Finish to Finish
e.Any of these could be correct
8. The lowest element in the hierarchical breakdown of the WBS is called ___________
a. A deliverable.
b. A work package
c. A cost account.
d. A lowest sub-deliverable.
e. An object.
9. Which of the following is true for a critical task?
a. It is a task which affects the project completion date if delayed
b. It has some slack time
c. It has some free slacks
d.It has some float
e. It is part of all the critical paths
10. Assume there are no holidays in between, how many days does it take to complete the below project?
a. 6 days
b. 8 days
c. 10 days
d. 17 days

For This or a Similar Paper Click To Order Now

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00